Creating & Managing Projects
Let's take a look at how to create, edit, delete, and associate incidents & changes with projects on ServiceDesk Plus OnDemand.
Contents
Creating a Project:
There are two ways to accessing a New Project Form in ServiceDesk Plus application,
- Quick Actions
- Projects Tab
Quick Actions
The Quick Actions menu is a quick navigator to instantly access the New Project form. Go to Quick Actions
>> New >> Project
Projects Tab
- Click the Projects tab in the header pane.
- Click the New Project button to open the New Project form.
- You can use the default Project template or choose a project template of your choice from the Choose Template box that lists all the saved Project templates.
- Specify the Project Title, Description and Code
- Select a Project Requester and Department (Of the Project Requester). The department will be auto-populated once you have selected a requester. You can change it if need be.
- Select the Project Type, Status and Priority from the drop-down list.
- Specify the Project Schedule Start and Schedule End date.

Adding more details to the Project:
To evaluate Project against the projected plan, you are provided with the following additional fields:
- Actual Start Date and Actual End Date (for recording real-time project completion date).
- Projected End (planned date for project completion)
- Estimated Hours and Actual Hours (fields recording 'planned and real-time' time taken for the Project).
- Estimated Cost and Actual Cost (fields recording 'planned and real-time' expenditure towards the Project).
- For adding attachments to the Project, click Attach File
.
Scheduling a Project:
Project Scheduling not only helps you schedule the project but also determine whether the project is 'on-schedule', 'delayed' or 'ahead' by comparing it against real-time completion.
To schedule the project, do the following:
- Configure the Scheduled Start and Scheduled End Date
- Fill in the Actual Start and Actual End Date (upon project completion)
- Based on Scheduled/Actual Dates, the project would be considered:
- On Schedule, if the Scheduled Date and Actual Date are the same.
- Delayed if the Project (Actual Date) has passed the Scheduled Date. (no of days by which project is delayed gets displayed on the project list view page)
- Ahead if the Project (Actual Date) is completed before the Scheduled Date. (no of days by which project is ahead gets displayed on the project list view page)
Editing a Project
- Select the Project in the Project List View page and click the Edit icon
.
- Implement the necessary changes and click Update Project.
You can also use the Settings icon right next to a project to edit the project.
Associating Change
The project can be used as a large scale change implementation which has its own members and tasks. To associate a project with existing Change, click the Search link under the Associated Change section in the RHS Panel. You will also be able to create a new change by clicking the New link.
An associated project can be dissociated by clicking Detach.
Copying a Project
You can copy projects into project templates as well as new projects.
To copy a project into a template, go to the project details page and click Copy as Project Template under Actions.
To copy a project into a new project, go to the project details page and click Copy Project under Actions.
You can also use the Settings icon right next to a project to copy the project.
Deleting a Project
From the project list view page, you can delete a project by clicking Settings
>> Delete. Alternatively, you can open the project details page and click Delete Project under Actions.